Progress Report
The builders moved on site today Monday 12th
May 2003.
We will give an update every month.
5th June 2003 Work
is progressing well.
23rd August
The builder has advised us that the building work is a week between.
24th September The
main Hall is virtually complete. The upstairs rooms are being floored and we
will hold a Church Service in the building on Sunday 5th October at 10-30am. The
builder has advised us that the work should be completed on time.
14th November At
the site meeting today the builder explained the delay and now hopes to finish
the building by 1st December. The room
above the Courtney Hall is now in use and the other upstairs room will be
finished on Monday. This now only leaves
the computer room and the Henly Room to be completed. The
photographs show the upstairs and the additional space that is now available. The
outside of the building and car park will be the last to be finished.
January 2004
 |
|
 |
| completed Building |
|
entrance Hall |
 |
|
 |
| down stairs |
|
Henly Room |
 |
|
 |
| down stairs |
|
Courtney hall |
 |
|
 |
| extended main hall |
|
used for Church Services |
 |
|
 |
| going up |
|
new |
 |
|
 |
| new |
|
computer room |
 |
|
 |
| upstairs |
|
new |
 |
|
 |
| new |
|
new kitchen |
February
2004
 |
|
|
|
|
entrance hall
|
 |
|
 |
| landing view |
|
new window |
 |
|
|
| new upstairs kitchen |
|
|
|