The builders moved on site today Monday 12th May 2003.
We will give an update every month.
5th June 2003
Work is progressing well.
23rd August
The builder has advised us that the building work is a week between.
24th September
The main Hall is virtually complete. The upstairs rooms are being floored and we will hold a Church Service in the building on Sunday 5th October at 10-30am. The builder has advised us that the work should be completed on time.
14th November
At the site meeting today the builder explained the delay and now hopes to finish the building by 1st December.
The room above the Courtney Hall is now in use and the other upstairs room will be finished on Monday.
This now only leaves the computer room and the Henly Room to be completed.
The photographs show the upstairs and the additional space that is now available.
The outside of the building and car park will be the last to be finished.
|
|
|
|
|
|
|
|
January 2004
![]() |
![]() |
|
| completed Building | entrance Hall | |
![]() |
![]() |
|
| down stairs | Henly Room | |
![]() |
![]() |
|
| down stairs | Courtney hall | |
![]() |
![]() |
|
| extended main hall | used for Church Services | |
![]() |
![]() |
|
| going up | new | |
![]() |
![]() |
|
| new | computer room | |
![]() |
![]() |
|
| upstairs | new | |
![]() |
![]() |
|
| new | new kitchen |
February 2004
![]() |
|
|
| entrance hall | ||
![]() |
![]() |
|
| landing view | new window | |
![]() |
||
| new upstairs kitchen |